Spirit Energy has extended the shutdown of its onshore North Morecambe gas processing terminal for a second time, now until 11 December. This follows an investigation into a methanol leak that was identified at the terminal on 11 October.

Investigation and Operational Impact

The initial containment and cleanup were completed, and operations were expected to restart last week. However, the investigation into the cause of the leak is taking longer than anticipated, necessitating the extended shutdown.

Safety and Environmental Context

The methanol discharge occurred during a planned maintenance shutdown that began on 7 September. No personnel were injured, and no environmental damage was reported from the incident.

Facility Background and Future

The North Morecambe terminal is a component of Spirit Energy's East Irish Sea Morecambe hub, which has been operational for 40 years. Historically, at its peak, the hub supplied approximately one-fifth of the UK's domestic gas demand. It is scheduled to remain in operation until around 2030, after which it will be transitioned into a carbon store as part of the Morecambe Net Zero project.



This material is an AI-assisted summary based on publicly available sources and may contain inaccuracies. For the original and full details, please refer to the source link. Based on materials by Rebecca Conan. All rights to the original text and images remain with their respective rights holders.

19 November 2025

Our solutions

icon

nv.analysis

Is a decision support solution designed to identify potential well candidates for workovers and provide reliable geological and technological information

  • icon

    Cloud / on-premise

  • icon

    Pre-project survey

  • icon

    Proof of concept

  • icon

    24/7 technical support

icon

nv.planning

Is a decision support solution intended for comprehensive operational planning of onshore and offshore upstream activities

  • icon

    Cloud / on-premise

  • icon

    Pre-project survey

  • icon

    Proof of concept

  • icon

    24/7 technical support

icon

nv.ID

Is a data storage solution for managing downhole equipment lifecycle

  • icon

    Cloud / on-premise

  • icon

    Pre-project survey

  • icon

    Proof of concept

  • icon

    24/7 technical support